The word Tariffs appears exactly once in Reata Pharmaceuticals' 15 October 2019 build-to-suit lease with TC Legacy Land Venture for 327,400 square feet in Plano, Texas, and it is not in the force majeure clause. It is in Section 5(b), where a duty enacted after the construction contract is signed raises Total Project Costs, lifts the $13,344,000 Maximum Base Rent at a 0.0760 Yield Constant, and then escalates 1.95% a year for a sixteen year term. Each dollar of tariff above the unspent contingency costs about $1.39 in rent. The same lease's force majeure definition says means only and lists material shortages and governmental moratoria, so the landlord gets time for a shortage and nobody gets time for a duty. Green Dot's Pasadena lease, ConforMIS's Billerica lease and a BioMed Realty form from San Diego draw the delay list three different widths, and none of the four carves out cost increases in so many words.
Section 4(b) of ICF Consulting's 24 October 2019 deed of lease at Reston Station builds a three-tier late delivery ladder on 208,274 square feet at $40.00, then gives the tenant ten business days after the 1 July 2022 Outside Delivery Date to use the termination right, and voids the notice if the landlord delivers inside the next thirty days. Miss that window and a four-month delay and a four-year delay pay the same. A June 2018 SharpSpring amendment doubled the per diem to two days and deleted the termination sentence outright. Juniper's Sunnyvale lease extends the grace period by force majeure with no cap, calls both remedies the sole remedy, and lets a landlord notice end the right to terminate. The Honest Company's lease filed in June 2026 has no outside date at all, and the filed text of its late delivery section is missing the words that would define the deadline.
A lease signed on 4 September 2026 for a converted power plant in Niagara Falls makes rent commencement wait on the utility. The Commencement Date Conditions are not satisfied until the full Critical Load Power for a phase is energized and available for continuous use at the demarcation point, and every interconnection and power-supply contract is in force. On 25 megawatts at the $145.00 per kW per month the lease uses for its design specifications, each month of delay is about $3.6 million of base rent the landlord cannot bill. The list of Excused Delays that moves the target date does not include utility delay, which a form lease filed by another developer the same week does include.
A St. Paul landlord asked its tobacco shop tenant to move to a bigger vacant unit in the same shopping center. The city denied the new license, because a St. Paul tobacco products shop license attaches to one address, there are fifteen of them citywide, and no new license may issue within 2,640 feet of an establishment that already holds one. Two units in one strip mall are not 2,640 feet apart. The Minnesota Court of Appeals affirmed the eviction on 20 July 2026: the force majeure clause extended deadlines rather than excusing performance, impossibility and frustration of purpose are unavailable in an eviction action, and a landlord that spends six months lobbying city hall for its tenant has not breached the duty of good faith.