A Late Delivery Termination Right That Expires Ten Business Days After It Arises

Section 4(b) of ICF Consulting's 24 October 2019 deed of lease at Reston Station builds a three-tier late delivery ladder on 208,274 square feet at $40.00, then gives the tenant ten business days after the 1 July 2022 Outside Delivery Date to use the termination right, and voids the notice if the landlord delivers inside the next thirty days. Miss that window and a four-month delay and a four-year delay pay the same. A June 2018 SharpSpring amendment doubled the per diem to two days and deleted the termination sentence outright. Juniper's Sunnyvale lease extends the grace period by force majeure with no cap, calls both remedies the sole remedy, and lets a landlord notice end the right to terminate. The Honest Company's lease filed in June 2026 has no outside date at all, and the filed text of its late delivery section is missing the words that would define the deadline.